When clearance is required
Any exterior works, structural changes, additions/roofing, driveway/utility cuts, façade changes visible from street, heavy deliveries causing road/staging use, o...
-
Gate & IDs
Submit Worker List with valid IDs; guards issue contractor passes. Passes must be shown on re...
-
Delivery windows
Regular deliveries: 8:00 AM – 6:00 PM.
Restricted hours (de...
-
Deposit
Amount: [₱ amount] (based on project scope), refundable after clearance.
...
-
Waste & hauling
Owner/contractor must haul debris off‑site to an LGU‑accredited...
-
Triggers
Working without clearance; ignoring approved hours; blocking emergency lanes; unsafe practices; dumping; damaging roads/drains without restoration.
...
-
Construction Clearance Application (fillable) — Owner; Lot/Blk; scope; drawings; timeline; contractor; Traffic/Delivery Plan; Waste/Restoration Plan; deposit amount; signatures.
...